Project:
Culvert Replacement
- Dumas, Arkansas
Installation
Date: April 2004
| Contractor required 450 feet of cofferdam
which was installed in three days and
allowed the contractor to replace the culvert five
days ahead of schedule. Once dewatered, the
contractor was able to work on dry land. |
| |
|
 |
 |
| Cofferdam site |
Installation Progress |
| |
|
 |
 |
Contractor utilized an 8" pump to pump
down the water ... |
... enabling construction on dry ground. |
|